Underfloor systems
Underfloor projects

After Installing Underfloor system...

After Installing Underfloor system


After Installing Underfloor system

Network Pipe Test

After the pipe installation and before the thermompeton casting (laying heating screed), a test of the network pipe is required applying three times the operating pressure.

Thermompeton Casting

The casting of thermompeton starts after the network has remained for at least 24 hours under pressure and is checked for any potential leaks.

~ Thermompeton composition per m3:

× 70% river or coarse sand.

× 250kg water.

× 300-350kg cement.

Superplasticizers × 2-2,5 kg (increase flexibility and prevent cracking of thermompeton).

× 900gr polypropylene fibers (increase the mechanical strength, reduce air bubbles and eliminate cracks).

Drying cement

The purpose of this process is to reduce the relative humidity of thermompeton.

Flooring

Flooring begins immediately after drying, using adhesives with high elasticity and proper quality materials guaranteed by the supplier, adhering to application instructions.

System Setup

Control of the temperature circuit is based on the study. Correct setting of the installation ensures good system performance.





Offers


Service
Service
System improvements
System improvements
Solar hotels
Solar hotels

Recent Projects

More projects
Papafi 55 P.S 546.38, Thessaloniki
Tel. 2310 911511, 2310907027
Fax 2310 911512
This site was co-financed by the European Regional Development Fund (ERDF) of the European Union

active³ 4.9 · © 2000 - 2013 IPS Ltd · Disclaimer