~ Placement of the hydraulic distribution table.
~ Placement of polyethylene sheet. In case the installation takes place on the top of a basement externally of your building, a polyethylene sheet is placed before loading insolating plate
~ Installation of perimeter tape – formation of expansion joints. The perimeter tape must allow the floor to move at least 5mm.
~ Configuration of internal joints. Joints are set up according to DIN18560.
~ Placement of insolating plate. Besides its heat insulation and soundproofing role, the panel acts as in support of underfloor heating pipes.
~Formation of the expansion joints in stairs
~ Laying of pipe plate junctions. Using a shape of cochlea (snail), the tube is adequately laid, permitting the heat to be transferred uniformly on the surface and the interior of the house.